STATUS

                                                                                          Project 569(02)

                                   District 7

       Claim # 07-020569-01

       Claim # 07-020569-02

 


Action                                                                                                             Date Complete

 

                        X         Notice of Intent to File a Claim received.                                                       9/6/05                         

                                                           

X         Letter to Contractor requesting Claim Documentation.                                       n/a                                                                   

X         Claim Documentation received from Contractor (5 copies to CO).                    9/6/05 &

10/28/05                                 

X         E-mail to District requesting Claim Documentation.                                            11/16/05                                                                     

X         Copy of District’s Claim Documentation sent to Contractor.                              12/23/05                                             

X         Hearing scheduled.                                                                                           1/17/06                                                                       

                                                Date:                Thursday, February 16, 2006                       

Time:                8:30 am

Location:          ODOT Central Office room 3C

 

X         Hearing date, time, and location confirmed with all parties.                                 1/17/06

 

0          Claim Documentation distributed to Panel.                                                                                

 

0          Names & phone numbers of those who may present information at the hearing. 

 

0          A/V needs for hearing identified.                                                                      

 

0                    Hearing conducted.                                                                                          

 

0          Decision issued.

                                               

0        Contractor either accepts or rejects decision in writing.

 

COMMENTS: